You are viewing PRM 2.2 Component parts of a prospectus as of . PRM 2.2 Component parts of a prospectus was last updated on 19/01/2026.

PRM 2.2 Component parts of a prospectus

19/01/2026R

A prospectus may be drawn up as a single document or as separate documents. 

Prospectus composed of separate documents

19/01/2026R

Subject to PRM 2.3, a prospectus composed of separate documents must be divided into: 

(1) a registration document

(2) a securities note; and

(3) where applicable, a summary.

19/01/2026G

Rules regarding the content of a registration document are set out in PRM 4.2 .

19/01/2026G

Rules regarding the content of a securities note are set out in PRM 4.3

19/01/2026G

Rules regarding the content of a summary are set out in PRM 2.5

19/01/2026G

Rules regarding a universal registration document are set out in PRM 2.6 .

Approval of component parts of a prospectus

19/01/2026R

A prospectus composed of separate documents will constitute a valid prospectus only once all of its component parts have been approved by the FCA

19/01/2026R

Where a registration document has already been approved by the FCA, an issuer must draw up the securities note and, where applicable, the summary, prior to the transferable securities being admitted to trading. The securities note and, where applicable, the summary will require separate approval by the FCA.

19/01/2026R

Once a registration document has been approved by the FCA, the registration document must be made available to the public without undue delay and in accordance with the arrangements set out in PRM 9.5 (Publication of the prospectus).

19/01/2026R

If, after the registration document has been approved by the FCA, a significant new factor, material mistake or material inaccuracy arises that: 

(1) relates to the information included in the registration document; and

(2) is capable of affecting the assessment of the transferable securities,

a supplement to the registration document must be submitted for approval in accordance with the rules at PRM 10 (Supplementary prospectus).

19/01/2026R

Where a summary is required, the supplement to the registration document referred to in PRM 2.2.10R must be submitted for approval no later than concurrently with the approval of the securities note and the summary.

19/01/2026R

Where the circumstances in PRM 2.2.10R apply, the right to withdraw acceptances in accordance with PRM 10.1.14R will not be available.

Approval of component parts of a prospectus: universal registration document

19/01/2026R

An issuer that has already had a universal registration document approved by the FCA, or that has filed a universal registration document without prior approval pursuant to PRM 2.6.3R, must draw up the securities note and, where applicable, the summary prior to the transferable securities being admitted to trading.

19/01/2026R

Where the universal registration document has already been approved by the FCA, the securities note, the summary and all amendments to the universal registration document filed since the approval of the universal registration document must be submitted for separate approval.

19/01/2026R

Where an issuer has filed a universal registration document without prior approval where applicable, the entire documentation, including amendments to the universal registration document, must be approved by the FCA, notwithstanding the fact that those documents remain separate.

19/01/2026R

The universal registration document, amended in accordance with PRM 2.6.8R(1) or PRM 2.6.12R, accompanied by the securities note and, where applicable, the summary will be a prospectus, once approved by the FCA.